Description
Delivery time: 50 days.
Chief montage : includes placement and assembly of equipment at the site of operation according to the approved scheme, internal electrical and pneumatic installation of equipment,
Customer :
- provides the required auxiliary workers, electricians, lifts and other agreed equipment for installation and assembly;
- ensures the supply of environments of the required quality necessary for the operation of equipment to the equipment connection points;
- guarantees the completion of construction work by the time of installation and adjustment of equipment.
Scheduled installation time - 10-12 days.
Start-up :
- connection of the installed equipment to the environments necessary for its operation,
- test idle start-ups of equipment,
- Debugging of equipment to operating parameters,
- launching equipment on the water,
- production of sterile test,
- release of a trial batch of the product,
- Running equipment in operation within 2 days.
The planned time-frame 10-12 days.
Staff training:
- training of operating personnel in the skills of working with equipment with the adoption of a qualification test - 7 days,
- compiling a list of personnel admitted to operation and service work on the equipment,
- training in maintaining service logs and accounting of equipment.